2.2
FALL PROTECTION ANCHORAGE
Fall protection anchorage, conforming to ANSI Z359.1, installed under the
supervision of a qualified person in fall protection, shall be left in
place for continued customer use and so identified by signage stating the
capacity of the anchorage (strength and number of persons who may be
tied-off to it at any one time).
PART 3
EXECUTION
3.1
CONSTRUCTION AND/OR OTHER WORK
The Contractor shall comply with USACE EM 385-1-1, NFPA 241, the APP, the
AHA, Federal and/or State OSHA regulations, and other related submittals
and activity fire and safety regulations. The most stringent standard
shall prevail.
3.1.1
Hazardous Material Use
**************************************************************************
NOTE: Include the following item in Navy projects
only.
**************************************************************************
Each hazardous material must receive approval prior to being brought onto
the job site or prior to any other use in connection with this contract.
Allow a minimum of 10 working days for processing of the request for use of
a hazardous material.
3.1.2
Hazardous Material Exclusions
Notwithstanding any other hazardous material used in this contract,
and devices used in accordance with USACE EM 385-1-1 such as nuclear
density meters for compaction testing and laboratory equipment with
or polychlorinated biphenyls, di-isocynates, lead-based paint are
prohibited. The Contracting Officer, upon written request by the
Contractor, may consider exceptions to the use of any of the above excluded
materials.
3.1.3
Unforeseen Hazardous Material
The design should have identified materials such as PCB, lead paint, and
friable and non-friable asbestos. If [additional] material, not indicated,
that may be hazardous to human health upon disturbance during construction
operations is encountered, stop that portion of work and notify the
Contracting Officer immediately. Within [14][_____] calendar days the
Government will determine if the material is hazardous. If material is not
hazardous or poses no danger, the Government will direct the Contractor to
proceed without change. If material is hazardous and handling of the
material is necessary to accomplish the work, the Government will issue a
modification pursuant to "FAR 52.243-4, Changes" and "FAR 52.236-2,
Differing Site Conditions."
3.2
PRE-OUTAGE COORDINATION MEETING
Contractors are required to apply for utility outages at least [15][_____]
SECTION 01525
Page 21