Government, the Contractor shall notify the Contracting Officer, in
writing, 5 working days before termination is desired. The Government will
take a final meter reading, disconnect service, and remove the meters. The
Contractor shall then remove all the temporary distribution lines, meter
bases, and associated paraphernalia. The Contractor shall pay all
outstanding utility bills before final acceptance of the work by the
Government.
1.2.5
Sanitation
The Contractor shall provide and maintain within the construction area
minimum field-type sanitary facilities approved by the Contracting Officer.
Government toilet facilities will not be available to Contractor's
personnel.
1.2.6
Telephone
The Contractor shall make arrangements and pay all costs for telephone
facilities desired.
1.3
BULLETIN BOARD, PROJECT SIGN, AND PROJECT SAFETY SIGN
1.3.1
Bulletin Board
Immediately upon beginning of work, the Contractor shall provide a
weatherproof glass-covered bulletin board not less than 915 by 1220 mm 36
by 48 inches in size for displaying the Equal Employment Opportunity
poster, a copy of the wage decision contained in the contract, Wage Rate
Information poster, and other information approved by the Contracting
Officer. The bulletin board shall be located at the project site in a
conspicuous place easily accessible to all employees, as approved by the
Contracting Officer. Legible copies of the aforementioned data shall be
displayed until work is completed. Upon completion of work the bulletin
board shall be removed by and remain the property of the Contractor.
1.3.2
Project and Safety Signs
The requirements for the signs, their content, and location shall be as
shown on the drawings. The signs shall be erected within 15 days after
receipt of the notice to proceed. The data required by the safety sign
shall be corrected daily, with light colored metallic or non-metallic
numerals. Upon completion of the project, the signs shall be removed from
the site.
1.4
PROTECTION AND MAINTENANCE OF TRAFFIC
During construction the Contractor shall provide access and temporary
relocated roads as necessary to maintain traffic. The Contractor shall
maintain and protect traffic on all affected roads during the construction
period except as otherwise specifically directed by the Contracting
Officer. Measures for the protection and diversion of traffic, including
the provision of watchmen and flagmen, erection of barricades, placing of
lights around and in front of equipment and the work, and the erection and
maintenance of adequate warning, danger, and direction signs, shall be as
required by the State and local authorities having jurisdiction. The
traveling public shall be protected from damage to person and property.
The Contractor's traffic on roads selected for hauling material to and from
the site shall interfere as little as possible with public traffic. The
Contractor shall investigate the adequacy of existing roads and the