USACE / NAVFAC / AFCESA
UFGS-01500A (February 1997)
----------------------------
Preparing Activity: USACE
Replacing without revision
CEGS of same number and date
UNIFIED FACILITIES GUIDE SPECIFICATIONS
**************************************************************************
SECTION 01500A
TEMPORARY CONSTRUCTION FACILITIES
02/97
**************************************************************************
NOTE: This guide specification covers the
requirements for temporary construction facilities.
Comments and suggestions on this guide specification
are welcome and should be directed to the technical
proponent of the specification. A listing of
technical proponents, including their organization
designation and telephone number, is on the Internet.
Recommended changes to a UFGS should be submitted as
a Criteria Change Request (CCR).
Use of electronic communication is encouraged.
Brackets are used in the text to indicate designer
choices or locations where text must be supplied by
the designer.
**************************************************************************
1.1
GENERAL REQUIREMENTS
**************************************************************************
NOTE: This guide specification includes
requirements which may be included in projects when
applicable. Requirements will be added, deleted, or
modified as necessary to meet project requirements.
**************************************************************************
1.1.1
Site Plan
The Contractor shall prepare a site plan indicating the proposed location
and dimensions of any area to be fenced and used by the Contractor, the
number of trailers to be used, avenues of ingress/egress to the fenced area
and details of the fence installation. Any areas which may have to be
graveled to prevent the tracking of mud shall also be identified. The
Contractor shall also indicate if the use of a supplemental or other
staging area is desired.
SECTION 01500A