ASCII file of report shall be provided to [Contracting Officer]
[HTRW CX] [_____].
PART 2
PRODUCTS (Not Applicable)
PART 3
EXECUTION
3.1
REPORT OUTLINE
The report outline shall be in accordance with EP 1110-1-19.
3.1.1
Executive Summary
The Executive Summary shall contain a brief overview of the Cost and
Performance Report. It shall include [a brief description of the
historical activities that generated the need for environmental
restoration,] [a brief summary of the appropriate regulatory framework
under which the cleanup is to occur,] [the remedial technology specified,]
[the date, number and title of decision document,] [any special sequencing
and scheduling milestones,] [definitions for standard terminology used in
the preparation of the report,] [average characteristics of the
contaminated media pre- and post-treatment,] [and] [the cost breakdown for
the complete remediation].
3.1.2
Site Information
**************************************************************************
NOTE: Site information data will be provided by
USACE and/or design contractor.
**************************************************************************
Information developed prior to remediation is [included] [_____].
3.1.2.1
Type of Action
It shall be stated whether the cleanup to be performed is an entire site
remediation or intermediate remedial project.
3.1.2.2
Period of Operation
The dates of start-up, shut-down, periods of retreatment, partial
operation, inactivity and operation of the treatment system shall be
indicated in the report.
3.1.2.3
Quantity of Material Treated During Application
The estimated quantity of material treated during the remedial or removal
action shall be indicated. For ex-situ or in-situ treatment, the estimated
volume of material treated shall be determined as specified in the
respective technical specification section and shall be noted in the report.
3.1.2.4
The clean-up goals associated with this project shall be shown in a
bulletized format.
3.1.2.5
Site Logistics/Contacts
The addresses and telephone numbers shall be listed for the [Project
SECTION 01240A
Page 6