d.
Failure to provide up to date record drawings not current as
stated in Contract Clause "FAC 5252.236-9310, Record Drawings."
1.7.2
Payment for Materials Offsite
**************************************************************************
NOTE: For LANTNAVFACENGCOM projects, this paragraph
shall only be used as directed by the Contracting
Officer.
**************************************************************************
Payments may be made to the Contractor for materials stored off
construction sites under the following conditions:
a.
Conditions described in the paragraph entitled "Payments to the
Contractor";
b.
Material within [a distance of [80] [_____] km [50] [_____] miles
by streets and roads to] [the county of] the construction site;
c.
Materials adequately insured and protected from theft and exposure;
d.
storage or in transit to the job site are acceptable for progress
payments. Items such as steel, machinery, pipe and fittings, and
electrical cable are acceptable; items such as gypsum wallboard,
glass, insulation, and wall coverings are not;
e.
Materials in transit to the job site or storage site are not
acceptable for payment; and
f.
Conditions specified in "FAR 52.232-5(b) Payments Under Fixed
Price Construction Contracts."
[1.7.3
Payment for Materials On Site
**************************************************************************
NOTE: Include this paragraph for projects located
at Guantanamo Naval Base.
**************************************************************************
Payment may be made for materials delivered to the site but not yet
incorporated into the construction. Materials on site shall be listed as a
separate item on he Contract Performance Statement. The value of the
materials shall be supported by the Schedule of Prices and a separate list
of all materials being invoiced shall be submitted with the invoice in the
following format:
MATERIAL ON
MATERIAL
MATERIAL
MATERIAL
SITE LAST
RECEIVED
CONSUMED
ON
ITEM PERIOD
+
THIS PERIOD
-
THIS PERIOD
=
SITE
]1.8
EQUITABLE ADJUSTMENTS:
WAIVER AND RELEASE OF CLAIMS
**************************************************************************
NOTE: For LANTNAVFACENGCOM, include the following
paragraph for projects in the Mediterranean.
**************************************************************************
SECTION 01200N
Page 9