the 12th of the month) in the following quantities:
a.
Contractor's invoice - Original and five copies
b.
Contractor's monthly estimate for voucher - Original and two
copies shall be required on jobs where there is a schedule of
prices
[c.
Affidavit - Original]
d.
Updated submittal register - Two copies
[e.
Progress schedule - Two copies]
[f.
Network mathematical analysis - Three copies]
g.
Contractor Safety Self Evaluation Checklist (original)
]1.7
PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor
which comply with the requirements of this section, and will be subject to
reduction for overpayments or increase for underpayments made on previous
payments to the Contractor.
**************************************************************************
NOTE: Use the following paragraph for
PACNAVFACENGCOM projects.
**************************************************************************
a.
Basis for Contracting Officer's consideration to allow progress
payment for material delivered on the site (but not installed) and
for completed preparatory work, as authorized under FAR
52.232-5(b), shall be (1) major high cost items and (2) long lead
special order items. Materials that will not be paid for prior to
installation include, but are not limited to, bulk quantities such
as nails, fasteners, conduits, gypsum board, etc. In the request
for progress payment, such items shall be specifically identified
in the Contractor's estimates of work submitted for the
Contracting Officer's approval in accordance with paragraph
entitled "Schedule of Prices" above. At the time of invoicing,
the amount billed shall be supported by documents establishing its
value.
1.7.1
Obligation of Government Payments
The obligation of the Government to make
payments required under the
provisions of this contract will, at the
discretion of the Contracting
Officer, be subject to reductions and/or
suspensions permitted under the
FAR and agency regulations including the
following in accordance with "FAR
32.503-6:
a.
Reasonable deductions due to defects in material or workmanship;
b.
Claims which the Government may have against the Contractor under
or in connection with this contract;
c.
Unless otherwise adjusted, repayment to the Government upon demand