submittal is sufficiently important or complex in
context of the project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for [Contractor Quality Control
approval.] [information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] The following shall be submitted in accordance with Section
01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
System design drawings conforming to NCTA RP.
SD-03 Product Data
Spare Parts
Spare parts data, as specified.
System Calculations
System calculations, [45] [_____] days prior to proposed
installation start date.
Testing
Test procedures and plans, [30] [_____] days prior to proposed
test date. The plan shall conform to NCTA RP and other applicable
codes, regulations, and manufacturer requirements. The plan shall
include proposed methods of documenting test results.
SD-06 Test Reports
Testing
Test reports in booklet form showing field tests performed to