Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for [Contractor Quality Control
approval.] [information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] The following shall be submitted in accordance with Section
01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Radio Paging System[; G][; G, [_____]]
Installation[; G][; G, [_____]]
material, including manufacturer's descriptive and technical
drawings shall also contain complete wiring and schematic
diagrams, system riser diagrams, and any other details required to
demonstrate that the system has been coordinated and will properly
function as a system. System riser diagrams shall include all
system components, all raceways, conductors, and elevation or plan
showing physical location of all components.
SD-03 Product Data
Field Training[; G][; G, [_____]]
Training plan outlining material covered and proposed schedule,
[30] [_____] days prior to start of courses.
Radio Paging System
[Six] [_____] copies of design manuals consisting of
manufacturer's standard literature. The design manual shall
the theory of operation, design philosophy, and specific
functions. A description of hardware and software functions,
interfaces, and requirements shall be included for all system
Spare Parts
Spare parts data, as specified.
Contractor Qualifications
Document certifying that Contractor meets specified
qualifications.
Manufacturer Qualifications
A statement attesting that manufacturer meets specified
SECTION 16755A