Control transfer panel
Control panel
Sequenced flashing light system components
Wave-Off system components complete
SD-06 Test Reports
Counterpoise system test
SD-07 Certificates
Installer Qualifications; G
Construction Outage Plan; G
SD-10 Operation and Maintenance Data
Rotating light beacon assembly, Data Package 3
Sequenced flashing light system, Data Package 5
Wave-Off system, Data Package 5
Submit in accordance with Section 01781 OPERATION AND
MAINTENANCE DATA.
1.4
QUALITY ASSURANCE
1.4.1
Qualifications
Do not install materials which are not approved as "Approved Airport
Equipment" by FAA unless specifically approved by the electrical design
engineer. Inspect wire and cable for date of manufacture. Do not use wire
and cable manufactured more than one year before delivery to job site.
1.4.2
Regulatory Requirements
Provide materials and equipment listed by FAA, UL, ETL or approved by
Factory Mutual Engineering and Research (FM), when such equipment is listed
or approved. Do not use askarel, tetrachlorethylene and insulating liquids
containing polychlorinated biphenyls (PCBs) in equipment. Provide
submersible type equipment installed below grade in vaults, manholes, and
handholes. Materials must be certified and listed as "Approved Airport
http://www.faa.gov/arp/pdf/534553ad.pdf.
1.4.3
Installer Qualifications
and installation electricians
must be experienced in installing, testing
and maintaining aviation
The contractor must provide a
list of government projects and 3 years of
experience in constructing
SECTION 16522N
Page 13