Contractors name and address, must name the project and location,
and must list the specific requirements which are being certified.]
1.4
DELIVERY, STORAGE, AND HANDLING
**************************************************************************
NOTE: ABC phasing should be in accordance with NFPA
70 front-to-back, top-to-bottom, and left-to-right.
Alternate phasing should be avoided, but where this
cannot be done, the drawings should clearly reflect
alternate phasing, and these specifications be
modified to include requirement for marking the
equipment.
**************************************************************************
The equipment shall be shipped as completely assembled and wired as
feasible so as to require a minimum of installation work. Each shipping
section shall be properly match marked to facilitate reassembly, and shall
be provided with removable lifting channels with eye bolts for attachment
of crane slings to facilitate lifting and handling. Any relay or other
device which cannot withstand the hazards of shipment when mounted in place
on the equipment shall be carefully packed and shipped separately. These
devices shall be marked with the number of the panel which they are to be
mounted on and fully identified. All finished painted surfaces and metal
work shall be wrapped suitably or otherwise protected from damage during
shipment. All parts shall be prepared for shipment so that slings for
handling may be attached readily while the parts are in a railway car or
transport truck. [Sections of equipment crated for shipment shall be of
such size, including crates, that they will pass through a [_____] by
[_____]-meter -foot hatch opening and a [_____] by [_____]-meter -foot wall
opening.] All spare parts and accessories shall be carefully packaged and
clearly marked.
1.5
MAINTENANCE
1.5.1
Accessories and Tools
A complete set of accessories and special tools unique to equipment
provided and required for erecting, handling, dismantling, testing and
maintaining the apparatus shall be furnished by the Contractor.
1.5.2
Spare Parts
**************************************************************************
NOTE: If three or more motors of the same size and
manufacturer are required, the designer should
specify more spare heater elements.
**************************************************************************
Spare parts shall be furnished as specified below. All spare parts shall
be of the same material and workmanship, shall meet the same requirements,
and shall be interchangeable with the corresponding original parts
furnished.
a.
2 - Fuses of each type and size.
b.
c.
2 - Operating coils for each size ac contactor.
SECTION 16403A
Page 13