on the equipment listed below. These services shall be performed
subsequent to testing but prior to the initial energization. The equipment
shall be inspected to ensure that installation is in compliance with the
Terminations of conductors at major equipment shall be inspected to ensure
the adequacy of connections. Bare and insulated conductors between such
terminations shall be inspected to detect possible damage during
installation. If factory tests were not performed on completed assemblies,
tests shall be performed after the installation of completed assemblies.
Components shall be inspected for damage caused during installation or
shipment to ensure packaging materials have been removed. Components
capable of being both manually and electrically operated shall be operated
manually prior to the first electrical operation. Components capable of
being calibrated, adjusted, and tested shall be calibrated, adjusted, and
tested in accordance with the instructions of the equipment manufacturer.
Items for which such services shall be provided, but are not limited to,
are the following:
a.
Secondary unit substation
b.
c.
d.
Switchboards
e.
Metal-enclosed switchgear
f.
Busways
g.
Switches
3.11.13
Operating Tests
After the installation is completed, and at such times as the Contracting
Officer may direct, the Contractor shall conduct operating tests for
approval. The equipment shall be demonstrated to operate in accordance
with the requirements herein. An operating test report shall be submitted
including the following:
a.
A list of equipment used, with calibration certifications.
b.
A copy of measurements taken.
c.
The dates of testing.
d.
The equipment and values to be verified.
e.
The condition specified for the test.
f.
The test results, signed and dated.
g.
A description of adjustments made.
3.12
MANUFACTURER'S FIELD SERVICE
**************************************************************************
NOTE: Delete if not required.
**************************************************************************
SECTION 16375A
Page 66