b.
Electrical Tests - Current Transformers
1.
2.
Perform polarity tests.
3.
Perform ratio-verification tests.
4.
Perform excitation test on transformers used for relaying
applications.
5.
Measure circuit burden at transformer terminals and determine the
total burden.
6.
When applicable, perform insulation resistance and dielectric
withstand tests on the primary winding with secondary grounded.
7.
CAUTION: Changes of connection, insertion, and removal of
instruments, relays, and meters shall be performed in such a
manner that the secondary circuits of energized current
c.
Electrical Tests - Voltage (Potential) Transformers
1.
2.
Perform a polarity test on each transformer to verify the polarity
marks or H1 - X1 relationships as applicable
3.
Perform a turns ratio test on all tap positions , if applicable.
4.
Measure potential circuit burdens at transformer terminals and
determine the total burden.
5.
Measure circuit burden at transformer terminals and determine the
total burden.
3.5.1.7
Battery Systems
a.
Visual and mechanical inspection
1.
Compare equipment nameplate data with specifications and approved
shop drawings.
2.
Inspect physical and mechanical condition.
3.
calibrated torque-wrench method. Thermographic survey[ is not] [
is] required.
4.
Measure electrolyte specific gravity and temperature and visually
check fill level.
5.
Verify adequacy of battery support racks, mounting, anchorage, and
clearances.
b.
Electrical tests
SECTION 16361N
Page 47