U.S. DEPARTMENT OF AGRICULTURE (USDA)
RUS 1728F-700
(1993) Wood Poles, Stubs, and Anchor Logs
RUS 1728H-701
(1993) Wood Crossarms Transmission Timbers
and Pole Keys
RUS 202-1
Use on Systems of RUS Electrification
Borrowers
UNDERWRITERS LABORATORIES (UL)
UL 510
(2005) Polyvinyl Chloride, Polyethylene,
and Rubber Insulating Tape
UL 6
(2000; Rev thru May 2003) Rigid Metal
Conduit
1.2
RELATED REQUIREMENTS
**************************************************************************
NOTE: This paragraph is to be included on Navy
projects only.
**************************************************************************
Section 16050N BASIC ELECTRICAL MATERIALS AND METHODS and Section 16081
APPARATUS INSPECTION AND TESTING apply to this section with additions and
modifications specified herein.
[1.3
OVERHEAD SERVICE
Terminate overhead service conductors into buildings at service entrance
fittings or weatherhead outside building. Installation and connection of
service entrance equipment to overhead service conductor is included in
Section 16402 INTERIOR DISTRIBUTION SYSTEM. Nearby support bracket for
overhead wires shall be not less than [_____] meters feet above finished
grade at building.
]1.4
SUBMITTALS
**************************************************************************
NOTE: Submittals must be limited to those necessary
for adequate quality control. The importance of an
item in the project should be one of the primary
factors in determining if a submittal for the item
should be required.
A "G" following a submittal item indicates that the
submittal requires Government approval. Some
submittals are already marked with a "G". Only
delete an existing "G" if the submittal item is not
complex and can be reviewed through the Contractor's
submittal is sufficiently important or complex in
context of the project.
For submittals requiring Government approval on Army
SECTION 16301N
Page 10