NOTE: This section utilizes the following energy
cost and loss value tables, found on CCB following
the directions above.
values required in Part 2 of the specification.
TABLE NUMBER
TITLE
OH-1
Impedance Data Cost (EC) Less Than or Equal to
||content||
.04 (2 pages)
OH-2
Impedance Data Cost (EC) Greater Than $.04 and
Less Than or Equal to
||content||
.08 (2 pages)
OH-3
Single-phase Pole-mounted Transformer Loss
& Impedance Data Cost (EC) Greater Than
$.08 and Less Than or Equal to
||content||
.12 (2 pages)
EC-1
Energy costs at LANTNAVFACENGCOM Activities
(2 pages)
EC-2
Energy costs at SOUTHNAVFACENGCOM Activities
(2 pages)
-----------------------------------------------------
**************************************************************************
**************************************************************************
NOTE: The following information should be shown on
the drawings:
1.
Conductor sizes, types, and materials.
2.
Guy strand type, size, and length.
3. Primary fused cutout; give voltage rating and
state fusing (ampere rating) and "K" quick or "T"
tardy required for coordination with existing
upstream sectionalizing equipment.
4. Pole top switch. State voltage, current, and
other operating characteristics. The applicable
switch ratings are stated in IEEE C37.30.
5. Meter connections (can be determined from NEMA
C12.10 or similar source).
6. Anchor type, description, and dimensions
suitable for the ultimate load and the specific soil
at location.
7. Indicate ruling span (average span length plus
2/3 of the difference between the longest and the
average span).
SECTION 16301N