For Converter:
[_____]
Checklist Item
Q
M
E
T
C
D
O
U
Installation
a.
Converter steam piping installed.
___ ___
X
___
X
___ ___ ___
b.
Converter steam piping tested.
___ ___
X
X
X
___ ___ ___
c.
Hot water piping installed.
___ ___
X
___ ___ ___ ___ ___
d.
Hot water piping tested.
___ ___
X
X
X
___ ___ ___
e.
Makeup water piping installed.
___ ___
X
X
X
___ ___ ___
f.
Vacuum breaker installed on shell of
shell and tube unit.
___ ___
X
X
X
___ ___ ___
g.
Air vent installed as specified.
___ ___
X
X
X
___ ___ ___
h.
Manufacturer's required maintenance
clearance provided.
___ ___
X
X
X
___ ___ ___
Startup
a.
Hot water system cleaned and filled.
___ ___
X
X
X
___ ___ ___
b.
All steam traps operational.
___ ___
X
X
X
___ ___ ___
c.
All condensate return pumps operational. ___ ___ ___
X
___ ___ ___ ___
d.
tested.
___ ___
X
X
X
___ ___ ___
e.
Converter startup and checkout complete. ___ ___
X
X
X
___ ___ ___
Controls
a.
Control valves/actuators properly
installed.
___ ___
X
___ ___ ___ ___ ___
b.
Control valves/actuators operable.
___ ___
X
___ ___ ___ ___ ___