COORDINATION OF TRADES
Furnish ductwork, piping offsets, fittings, and accessories as required to
provide a complete installation and to eliminate interference with other
construction.
1.3
DELIVERY AND STORAGE
Store equipment at the jobsite so that it is protected from the weather,
humidity and temperature variations, dirt and dust, or other contaminants.
Additionally, cap or plug all pipes until installed.
1.4
FIELD MEASUREMENTS
After becoming familiar with all details of the work, the Contractor shall
verify all dimensions in the field, and shall advise the Contracting
Officer of any discrepancy before performing the work.
1.5
SUBMITTALS
**************************************************************************
NOTE: Submittals must be limited to those necessary
for adequate quality control. The importance of an
item in the project should be one of the primary
factors in determining if a submittal for the item
should be required.
A "G" following a submittal item indicates that the
submittal requires Government approval. Some
submittals are already marked with a "G". Only
delete an existing "G" if the submittal item is not
complex and can be reviewed through the Contractor's
submittal is sufficiently important or complex in
context of the project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.