projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for [Contractor Quality Control
approval.] [information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] The following shall be submitted in accordance with Section
01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Detailed Drawings
Detailed drawings for the specific equipment being proposed, as
specified.
Boiler Setting
Complete setting plans, certified by the boiler manufacturer.
SD-03 Product Data
Support Steel
walls, roof, foundations, and other features for specialty type of
construction, with design data for lateral forces that may be
encountered due to wind loads and seismic forces. The design data
shall include manufacturer's equipment design data.
Spare Parts
The Contractor shall furnish spare parts data for each item of
equipment provided, as specified.
Welding
A copy of qualified procedures and a list of names and
Framed Instructions
Posted diagrams, instructions, and other sheets, before posting.
Framed instructions shall be posted before acceptance testing of
the systems.
Performance Tests[; G][; G, [_____]]
A proposed performance test procedure for the operating [and
environmental] tests, 30 days prior to the proposed test date.
The procedure shall contain a complete description of the proposed
test with calibration curves or test results furnished by an
independent testing laboratory of each instrument, meter, gauge,
and thermometer to be used in the tests. The test shall not
commence until the procedure has been approved. The Contractor's
complete plan for water treatment, including proposed chemicals to
be used and nationally recognized testing codes applicable to the