Conduct the test for each CRACU for a continuous 24-hour test period. A
CRACU shutdown before the continuous 24-hour test period is completed shall
result in the 24-hour test period being started again and run for the
required duration.
3.3.5
Deficiency Resolution
The test requirements shall be acceptably met; deficiencies identified
during the tests shall be corrected in compliance with the manufacturer's
recommendations. Corrections shall be tested again in compliance with the
requirements specified in the paragraph "Field Test Plans".
3.3.6
Field Test Reports
Use the test reporting forms approved in the field test plan. Final test
report forms shall be typed, including data entries and remarks. Completed
test report forms for each CRACU shall be reviewed, approved, and signed by
the Contractor's test director and the QC manager.
-- End of Section --