1.5.2
Engineer's Qualification Resume
Submit a printed certified qualification resume of the engineer or
technician to the Contracting Officer. The engineer or technician's resume
shall list applicable experience related to installation, start-up and
testing of equipment and applicable factory training and education.
Qualifications require the engineer to have supervised two installations of
similar size and type which are operating satisfactorily. More than one
engineer or technician may be provided based on the types of specific
equipment. In event more than one engineer or technician is provided,
provide a certified resume for each one and indicate his specific specialty
and item of work on the resume.
1.5.3
Start-Up, Testing, and Installation Engineer
The Contractor shall provide the services of a qualified engineer or
technician for start-up, testing, and installation of equipment as
specified under paragraph entitled "Qualifications of Engineer." The
engineer or technician shall be an employee of the equipment manufacturer.
1.5.4
Installation
Provide an installation engineer or technician to install and supervise the
controls. Provide the technician or engineer until equipment installation
is coordinated and completed with checkout.
1.5.5
Start-Up Plan
Submit a written schedule with dates of start-up, test, installation and
checkout of equipment to the Contracting Officer.
1.5.6
Start-Up and Test
The specific equipment tested
shall be the boiler, boiler controls, boiler
equipment. The start-up and testing engineer
or technician shall remain on
the job until the unit has been successfully
operated for [_____] days and
the unit has been accepted by the Contracting
Officer.
1.5.7
Start-Up Certification
After installation of equipment, submit a certificate or certified written
statement, signed by the engineer or technician, that the equipment is
installed in accordance with the manufacturer's recommendations.
PART 2
PRODUCTS
2.1
**************************************************************************
NOTE: Steam-atomizing burners should be specified
kPa (gage) 100 psig.
**************************************************************************
**************************************************************************
NOTE: Oil burners can have turndown ratio of 4,5,
or 6 to 1.
SECTION 15517N
Page 10