Contracting Officer, upon receipt of 14 calender days advance notice from
the Contractor, shall request the boiler be inspected by a NAVFACENGCOM
Boiler Inspector. The Contractor shall perform final operational
NAVFACENGCOM Boiler Inspector, at the discretion of the NAVFACENGCOM Boiler
Inspector. The NAVFACENGCOM Boiler Inspector shall receive copies, and
review the results, of all pertinent operational test reports before
approving acceptance of the boiler plant by the Government.
3.2.6
Manufacturers Field Services
3.2.6.1
Erection/Installation Supervisors and Service Engineers
a.
Boiler: Furnish the services of a competent supervisor who is in
the direct employ of the boiler manufacturer. Supervisor shall
remain on the construction site the full 8 hours per day, 5 days
per week, or the same hours, that the boiler installation takes
place. Supervisor shall be responsible for the complete steam
generating unit, including steam generator, stoker, [burner,] fans
and related work, such as refractory, or insulation regardless of
whether stoker, [burner,] fans or other related items of work are
furnished by manufacturers other than the boiler manufacturer.
b.
Stoker: Furnish a competent erection supervisor for the equipment
furnished by the stoker manufacturer.
c.
Fans: Furnish a company service engineer to advise on the
erection or installation of fans and related equipment.
d.
Service Engineers: Services of the manufacturing companies'
service engineers and the system suppliers' service engineers
shall be provided by the Contractor to advise during erection and
installation of other systems and equipment such as control
system, coal handlings system, ash handling system, air
condensate pumps, water treatment equipment, chemical feed pumps,
deaerating feedwater heater and stacks.
3.2.6.2
Boiler and System Representatives
a.
Furnish factory trained engineers or technicians who are
representatives of the boiler manufacturer and system suppliers to
b.
Furnish the services of a Boiler Inspector who is qualified and
certified as such by the National Board of Boiler and Pressure
Vessel Inspectors and who is presently employed full time by an
independent firm, such as Hartford Steam Boiler Inspection and
3.2.7
Instruction to Government Personnel
In accordance with the provisions of Section 15050N BASIC MECHANICAL
MATERIALS AND METHODS, supervisors and service engineers shall provide
instruction for the Government's operators in the operation and maintenance
of the equipment furnished under this section. The minimum number of hours
provided shall be as follows: