PART 1
GENERAL
1.1
REFERENCES
**************************************************************************
NOTE: Issue (date) of references included in
provided by the latest guide specification. Use of
SpecsIntact automated reference checking is
recommended for projects based on older guide
specifications.
**************************************************************************
The publications listed below form a part of this specification to the
extent referenced. The publications are referred to within the text by the
basic designation only.
ASME INTERNATIONAL (ASME)
ASME HST-5
(1999; R 2004) Air Chain Hoists
ASME HST-6
ASTM INTERNATIONAL (ASTM)
ASTM A 275/A 275M
(2003) Magnetic Particle Examination of
Steel Forgings
MONORAIL MANUFACTURERS ASSOCIATION (MMA)
MMA MH27.1
(2003) Underhung Cranes and Monorail
Systems
1.2
VERIFICATION OF DIMENSIONS
The Contractor shall be responsible for the coordination of his work with
the work of all trades involved and as it relates to the building
structure. The Contractor shall verify all building dimensions that relate
to fabrication of the monorail system, and shall notify the Contracting
Officer of any discrepancy before order to the monorail manufacturer is
finalized.
1.3
SUBMITTALS
**************************************************************************
NOTE: Submittals must be limited to those necessary
for adequate quality control. The importance of an
item in the project should be one of the primary
factors in determining if a submittal for the item
should be required.
A "G" following a submittal item indicates that the
submittal requires Government approval. Some
submittals are already marked with a "G". Only
delete an existing "G" if the submittal item is not
complex and can be reviewed through the Contractor's
submittal is sufficiently important or complex in
context of the project.
SECTION 14535N