Sprinkler System Installer, concurrent with submittal of the Fire
Protection Specialist Qualifications.
Fire Protection Related Submittals
A list of the Fire Protection Related Submittals, no later than
[7] [_____] days after the approval of the Fire Protection
Specialist.
Sway Bracing
For systems that are required to be protected against damage
from earthquakes, load calculations for sizing of sway bracing.
Materials and Equipment[; G][; G, [_____]]
Manufacturer's catalog data included with the Sprinkler System
Drawings for all items specified herein. The data shall be
highlighted to show model, size, options, etc., that are intended
for consideration. Data shall be adequate to demonstrate
compliance with all contract requirements. In addition, a complete
and quantity shall be provided.
Hydraulic Calculations[; G][; G, [_____]]
Hydraulic calculations, including a drawing showing hydraulic
reference points and pipe segments.
Storage Batteries[; G][; G, [_____]]
Calculations to substantiate the total requirements for
supervisory and alarm power. Ampere-hour requirements for each
system component and each control panel component or module, under
both normal and alarm conditions shall be included. The battery
recharging period shall be included with the calculations.
Spare Parts
Spare parts data for each different item of material and
equipment specified.
Preliminary Tests[; G][; G, [_____]]
Proposed procedures for Preliminary Tests, no later than [14]
[_____] days prior to the proposed start of the tests.
Proposed date and time to begin Preliminary Tests, submitted
with the Preliminary Tests Procedures.
Final Acceptance Tests[; G][; G, [_____]]
Proposed procedures for Final Acceptance Tests, no later than
[14] [_____] days prior to the proposed start of the tests.
Proposed date and time to begin Final Acceptance Tests,
submitted with the Final Acceptance Test Procedures. Notification
shall be provided at least [14] [_____] days prior to the proposed
start of the test. Notification shall include a copy of the
SECTION 13945A