Shop Drawings[; G][; G, [_____]]
[Three] [_____] copies of the Sprinkler System Drawings, no
later than [21] [_____] days prior to the start of sprinkler
system installation. The Sprinkler System Drawings shall conform
to the requirements established for working plans as prescribed in
NFPA 13. Drawings shall include plan and elevation views
demonstrating that the equipment will fit the allotted spaces with
clearance for installation and maintenance. Each set of drawings
shall include the following:
a. Descriptive index of drawings in the submittal with drawings
listed in sequence by drawing number. A legend identifying device
symbols, nomenclature, and conventions used.
b. Floor plans drawn to a scale not less than 1:100 1/8" = 1'-0"
which clearly show locations of sprinklers, risers, pipe hangers,
seismic separation assemblies, sway bracing, inspector's test
connections, drains, and other applicable details necessary to
clearly describe the proposed arrangement. Each type of fitting
used and the locations of bushings, reducing couplings, and welded
joints shall be indicated.
c. Actual center-to-center dimensions between sprinklers on
branch lines and between branch lines; from end sprinklers to
adjacent walls; from walls to branch lines; from sprinkler feed
mains, cross-mains and branch lines to finished floor and roof or
ceiling. A detail shall show the dimension from the sprinkler and
sprinkler deflector to the ceiling in finished areas.
d. Longitudinal and transverse building sections showing
typical branch line and cross-main pipe routing as well as
elevation of each typical sprinkler above finished floor.
e. Details of each type of riser assembly; air supply system
and piping; pipe hanger; sway bracing for earthquake protection,
and restraint of underground water main at point-of-entry into the
building, and electrical devices and interconnecting wiring.
As-Built Drawings
As-built shop drawings, at least [14] [_____] days after
completion of the Final Tests. The Sprinkler System Drawings
shall be updated to reflect as-built conditions after all related
work is completed and shall be on reproducible full-size mylar
film.
SD-03 Product Data
Fire Protection Related Submittals
A list of the Fire Protection Related Submittals, no later than
[7] [_____] days after the approval of the Fire Protection
Specialist.
Sway Bracing
For systems that are required to be protected against damage
from earthquakes, load calculations for sizing of sway bracing.
SECTION 13935A
Page 12