Materials and Equipment[; G][; G, [_____]]
Manufacturer's catalog data included with the Sprinkler System
Drawings for all items specified herein. The data shall be
highlighted to show model, size, options, etc., that are intended
for consideration. Data shall be adequate to demonstrate
compliance with all contract requirements. In addition, a
number and quantity shall be provided.
Hydraulic Calculations[; G][; G, [_____]]
Hydraulic calculations, including a drawing showing hydraulic
reference points and pipe segments.
Spare Parts
Spare parts data shall be included for each different item of
material and equipment specified.
Preliminary Tests[; G][; G, [_____]]
Proposed procedures for Preliminary Tests, no later than [14]
[_____] days prior to the proposed start of the tests. Proposed
date and time to begin the preliminary tests.
Final Acceptance Test[; G][; G, [_____]]
Proposed procedures for Final Acceptance Test, no later than
[14] [_____] days prior to the proposed start of the tests.
Proposed date and time to begin Final Acceptance Test, submitted
with the Final Acceptance Test Procedures. Notification shall be
provided at least [14] [_____] days prior to the proposed start of
the test. Notification shall include a copy of the Contractor's
Material & Test Certificates.
On-site Training[; G][; G, [_____]]
Proposed On-site Training schedule, at least 14 [_____] days
Fire Protection Specialist[; G][; G, [_____]]
The name and documentation of certification of the proposed Fire
Protection Specialists, no later than 14 days [_____] after the
Notice to Proceed and prior to the submittal of the sprinkler
system drawings and hydraulic calculations.
Sprinkler System Installer[; G][; G, [_____]]
The name and documentation of certification of the proposed
Sprinkler System Installer, concurrent with submittal of the Fire
Protection Specialist Qualifications.
SD-06 Test Reports
Preliminary Test Report[; G][; G, [_____]]
[Three] [_____] copies of the completed Preliminary Test Report,
SECTION 13930A