some applicable laws forbid this approach and will
dictate when the PQP, the NC or both will be
required to perform the function involved. However,
the Contractor shall always hire a PQP.
**************************************************************************
[Direct the PQP to record and report, to the Contracting Officer, the
amount of asbestos containing material removed and released for disposal.
Deliver the report for the previous day at the beginning of each day shift
with amounts of material removed during the previous day reported in linear
meters or square meters linear feet or square feet as described initially
in this specification and in cubic meters feet for the amount of asbestos
containing material released for disposal.]
[Allow the NC to inspect, record and report the amount of asbestos
containing material removed and released for disposal on a daily basis.]
-- End of Section --
SECTION 13281N
Page 35