testing and adjustment, including testing of coating for thickness
and holidays. Installation of materials and equipment shall not
commence until this submittal is approved.
Spare Parts
Spare parts data for each different item of material and
equipment specified.
SD-06 Test Reports
Testing, Adjusting, and Placing in Service
Test reports in booklet form tabulating all field tests and
measurements performed, upon completion and testing of the
installed system and including potential survey, final system test
verifying protection, and holiday coating test. Each test report
shall indicate the final position of controls. A certified test
report showing that the connecting method has passed a 120-day
laboratory test without failure at the place of connection,
wherein the anode is subjected to maximum recommended current
output while immersed in a 3 percent sodium chloride solution.
Contractor's Modifications[; G][; G, [_____]]
Final report including measurements throughout the tank area,
indicating that the addition of anodes corrected the conditions
which made the additional anodes necessary. The following are
required: Installation and testing procedures, anode number,
life, and parameters to achieve protective potential.
SD-07 Certificates
Cathodic Protection System
Proof that the materials and equipment furnished under this
section conform to the specified requirements contained in the
referenced standards or publications. The label or listing by the
specified agency will be acceptable evidence of such compliance.
Services of "Corrosion Expert"[; G][; G, [_____]]
Evidence of qualifications of the "corrosion expert."
(a) The "corrosion expert's" name and qualifications shall be
certified in writing to the Contracting Officer prior to the start
of construction.
(b) Certification shall be submitted giving the name of the
firm, the number of years of experience, and a list of not less
than five (5) of the firm's installations three (3) or more years
old that have been tested and found satisfactory.
SD-10 Operation and Maintenance Data
Cathodic Protection System
[Six] [_____] copies of operating manual outlining the
step-by-step procedures required for system startup, operation,
SECTION 13111A
Page 7