Administrative Data:
Test personnel.
Contract number.
Date of test.
Authentication. Contractor personnel responsible for performance
of the tests and witnessing organization or representatives.
Contents:
Shielded facility description.
Nomenclature of measurement equipment.
Serial numbers of measurement equipment. Date of last calibration of
measurement equipment. Type of test performed. Measured level of
reference measurements and ambient level at each frequency and test point.
Measured level of attenuation in decibels at each frequency and test point.
Dynamic range at each test frequency and test point. Test frequencies.
Location on the shielded enclosure of each test point. Actual attenuation
level at each test point.
Conclusions: This section shall include results of the tests in
brief narrative form.
Number of Copies of the Report:
[Three] [_____] copies.
3.7.2
Field Testing
**************************************************************************
NOTE: If a facility is required to fully comply
with MIL-STD-188-125 by the Joint Chiefs of Staff, a
military department headquarters, or a major
command, coordinate with the using organization to
the testing required by appendix A of that standard
should be performed. However, the using
organization may insist on full testing in
accordance with appendix B as well. In that case,
advise the user that, based on limited testing to
date, no existing EM filter/ESA devices have
survived the E-2 and E-3 waveforms. Include
appropriate cost and scheduling considerations if
appendix B testing is required. If MIL-STD-188-125
is not a requirement, avoid its reference.
**************************************************************************
Testing shall be accomplished in the three parts described below.
3.7.2.1
Testing - Part 1
Part 1 shall be in-progress testing and shall include inspection, visual
seam inspection, and seam testing of all EM shielding materials and
installation. [In-progress testing of welded shielding shall include
testing the structural welds to be embedded prior to concrete placement by
dye penetrant and magnetic particle testing and 100 percent testing of
wall, ceiling, and floor shielding welds by the SELDS tests.] [In-progress
testing of bolted construction shall include 100 percent testing of floor,
wall, and ceiling shielding seams by the SELDS testing.] After successful
SECTION 13095A