2.5.3
Doors
Welded double pan construction with sound deadening material inside.
2.5.4
Drawers
Double pan fronts, with guides as specified for wood cabinets.
2.5.5
Doors and Drawer Fronts
Doors and Drawer Fronts may be as specified for wood cabinets in lieu of
metal pan construction.
2.5.6
Shelves
Form with 90 degree bends on all four edges and two additional 90 degree
bends on front edge.
2.5.7
Countertops
As specified for wood cabinets.
2.5.8
Finish
High-baked acrylic enamel, color [as selected from manufacturer's standard
]PART 3
EXECUTION
3.1
INSTALLATION
**************************************************************************
NOTE: The following paragraph should be included
under installation in Section 15400, "Plumbing
Systems" of the project specification:
"Countertop Sinks [and Lavatories]: Set fixtures
with a bead of sealant all around to produce a
watertight joint. Secure fixtures in place with
mounting rims of type specified."
**************************************************************************
Install cabinets and countertops level, plumb, true to line, and tight
against adjacent walls. Secure cabinets to walls with concealed screws or
toggle bolts, and secure tops to cabinets with concealed screws. Provide
closer and filler strips and finish moldings as required for a complete and
finished installation. Draw joints in countertops up tight with special
concealed fasteners. Joints shall be flush within 0.250 mm 0.010 inch,
shall not gap more than 0.50 mm 0.020 inch, and shall be watertight. Cut
countertops which are to receive sinks [or lavatories] to templates
furnished by sink [or lavatory] manufacturer. Align doors, adjust
hardware, and clean all surfaces.
-- End of Section --