3.4.2.2
Water
The water [utility] [company] is [_____], telephone number [_____].
3.4.2.3
Natural Gas
The natural gas [utility] [company] is [_____], telephone number [_____].
3.4.3
Fuel System
**************************************************************************
NOTE: Coordinate requirements for the fuel source
specified in paragraph Feed Capability.
**************************************************************************
Fuel system installation and testing shall comply with the applicable
requirements of NFPA 30 and NFPA 31, NFPA 54 or NFPA 58, as appropriate to
the type of fuel.
3.5
FIELD QUALITY CONTROL/TESTS
3.5.1
Pressure and Leakage Test
**************************************************************************
NOTE: Testing of pipe and fittings should be
specified in the pipe specification. The test
pressure for vessels should not exceed the rated
pressure.
**************************************************************************
After installation, all piping, equipment, joints and connections shall be
tested for gas tightness. Connections and piping shall be tested by
subjecting the complete system to pneumatic pressure of not less than [
[105] [_____] kPa [15] [_____] psi] [the pressure indicated in the
schedule] for 6 hours. During the test, the system shall be disconnected
from the source of pressure and, with corrections made for barometric and
temperature changes, the pressure shall remain constant for the test
period, as indicated by a test gauge. Joints shall be tested using a soapy
water solution to detect leaks.
3.5.2
Operational/Performance Tests
**************************************************************************
NOTE: Coordinate with the blower specification and
the design sequence of operation. Testing
requirements should be edited to fit the intended
mode of operation for the system. Flow rates for
operating capacity tests will be inserted in the
blank spaces provided.
**************************************************************************
After installation and pressure testing, the entire off-gas system shall be
subjected to [an operational test] [a performance test] to demonstrate
satisfactory functional efficiency. Results of the tests shall be used in
determining the capacity and performance of the oxidation unit. Any
deficiencies revealed during the tests shall be corrected and the tests
repeated.