additional cost to the Government. Power usage shall also be evaluated at
25, 50, and 75 percent of the design production rate.
3.11
MANUFACTURER'S SERVICES
**************************************************************************
NOTE: Use this paragraph when manufacturers are to
provide field quality control with onsite personnel
for instruction/supervision of the installation or
application of their products, or for startup or
demonstration.
This paragraph covers requirements of the installer
or manufacturer to demonstrate the operation and
maintenance of equipment to the owner's personnel.
**************************************************************************
The manufacturer shall provide a qualified service representative
experienced in the installation, adjustment, operation and maintenance of
the equipment specified for a minimum of [3] [_____] days. The
representative shall supervise the installation, adjustment, testing, and
shall provide instruction in the operation, and maintenance of the
equipment. If major components from multiple suppliers are provided, such
as an [ozone generator] [air preparation system] [oxygen preparation
system] [ozone destruct system] [_____], each supplier shall be required to
visit the site a minimum of [1] [_____] times during equipment installation
or startup. During the startup and [one] [_____] years operating period,
the major equipment suppliers shall be required to be onsite [2] [_____]
times to verify that the equipment is installed and operates properly, and
to provide trouble shooting and technical assistance.
3.12
FIELD TRAINING
A field training course shall be provided for designated operating and
maintenance staff members. The training shall include operation of
individual components as well as the integrated system, maintenance needs
and procedures, instrument calibration, safety issues and emergency
procedures, control and alarm features, troubleshooting equipment and
control problems, and laboratory analytical procedures. Training shall be
provided during normal working time and shall start after the system is
shall cover all of the items contained in the operating and maintenance
manuals. Each major equipment vendor including, but not limited to, the
ozone generator, ozone destruct system, ozone monitoring system, and gas
feed system shall be required to provide two [8] [_____] hour periods of
the Contracting Officer. The first period shall be at system startup and
the second [as defined by the Contracting Officer] [at the end of the
Contractor's operating contract, prior to turning over to the long term
facility operator].
3.13
MAINTENANCE
3.13.1
Maintenance Service
**************************************************************************
NOTE: Delete this paragraph if UV lamps are not
used. The designer may want to provide additional
information regarding lamp change out if the system
SECTION 11377
Page 39