Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for [Contractor Quality Control
approval.] [information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] The following shall be submitted in accordance with Section
01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Lath
Drawings showing details of construction for reinforcement,
furring, and grounds; including manufacturer's installation
instructions for stucco materials, and locations where each mix
and coating thickness will be used.
SD-03 Product Data
Materials
Detailed description of the proposed job-mix proportions for
base and finish coats; including identification of thickness of
coats.
SD-04 Samples
Colored Stucco Finish Coat
Samples including both a fabricated portion of unit of work and
color samples.
Sample Panel
Sample panel, as specified.
1.3
DELIVERY AND STORAGE
Packaged materials shall be delivered to the site in the original packages
and containers with labels intact and seals unbroken. Cementitious
materials shall be kept dry and stored off the ground under cover away from
damp surfaces until ready to be used. Aggregate shall be covered to
prevent the absorption or loss of moisture.
SECTION 09225
Page 5