[For Navy projects, install one of each type of penetration and have it
inspected and accepted by the [_____] Division, Naval Facilities
Engineering Command, Fire Protection Engineer prior to the installation of
the remainder of the penetrations. At this inspection, the manufacturer's
technical representative of the firestopping material shall be present.]
For all projects,[ the remainder of] [the firestopped areas] shall not be
covered or enclosed until inspection is complete and approved by the
manufacturer's technical representative. The manufacturer's representative
shall inspect the applications initially to ensure adequate preparations
(clean surfaces suitable for application, etc.) and periodically during the
work to assure that the completed work has been accomplished according to
the manufacturer's written instructions and the specified requirements.
The Contractor shall submit written reports indicating locations of and
types of penetrations and types of firestopping used at each location; type
shall be recorded by UL listed printed numbers.
-- End of Section --
SECTION 07840
Page 9