A "G" following a submittal item indicates that the
submittal requires Government approval. Some
submittals are already marked with a "G". Only
delete an existing "G" if the submittal item is not
complex and can be reviewed through the Contractor's
submittal is sufficiently important or complex in
context of the project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for
the Government.] The following shall be submitted in accordance with
Section 01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
**************************************************************************
NOTE: Specify shop drawings for wood nailers when
nailers are required for securing insulation on
roofs sloped one in 24 1/8 inch per foot or more.
**************************************************************************
[Wood nailers]
[Tapered roof insulation system; G, [_____]]
[Taper cants and crickets]
**************************************************************************
NOTE: Include requirement for backnailing felts
when backnailing of felts is specified for built-up
roofing. Include bracketed second and third
sentences when tapered insulation is specified.
**************************************************************************
[Show location and spacing of wood nailers that are required for
securing insulation [and for backnailing of roofing felts]].
SECTION 07220
Page 6