Zone 2 or greater, include the following paragraph.
**************************************************************************
In addition to AISC 325, the structural steel system shall be provided in
accordance with AISC 341.
]1.7
QUALITY ASSURANCE
1.7.1
Drawing Requirements
Submit fabrication drawings for approval prior to fabrication. Prepare in
accordance with AISC 326, AISC 316 and AISC 317. Drawings shall not be
reproductions of contract drawings. Include complete information for the
fabrication and erection of the structure's components, including the
location, type, and size of bolts, welds, member sizes and lengths,
connection details, blocks, copes, and cuts. Use AWS A2.4 standard welding
symbols. [Shoring and temporary bracing shall be designed and sealed by a
registered professional engineer and submitted for record purposes[, with
calculations,] as part of the drawings.]
1.7.2
Certifications
1.7.2.1
Overhead, Top Running Crane Rail Beam
Submit written field survey results for overhead, top running crane rail
beam verifying tolerance requirements, area out of tolerance and proposed
1.7.2.2
Erection Plan
Submit for record purposes. Indicate the sequence of erection, temporary
shoring and bracing, and a detailed sequence of welding, including each
welding procedure required.
1.7.2.3
Welding Procedures and Qualifications
Prior to welding, submit certification for each welder stating the type of
welding and positions qualified for, the code and procedure qualified
under, date qualified, and the firm and individual certifying the
qualification tests. If the qualification date of the welding operator is
more than one-year old, the welding operator's qualification certificate
shall be accompanied by a current certificate by the welder attesting to
the fact that he has been engaged in welding since the date of
certification, with no break in welding service greater than 6 months.
PART 2
PRODUCTS
2.1
STEEL
**************************************************************************
NOTE: Materials appropriate to the design will be
selected and remaining materials will be deleted.
Designer should require materials, products, and
innovative construction methods and techniques which
are environmentally sensitive, take advantage of
recycling and conserve natural resources.
**************************************************************************
SECTION 05120
Page 12