"G" designation identifies the office that will review the submittal for
the Government.] The following shall be submitted in accordance with
Section 01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Reinforcing steel; G, [_____]
Formwork
Construction joints
Reproductions of contract drawings are unacceptable.
SD-03 Product Data
Waterstops
Materials for curing concrete
Joint sealants
Joint filler
Synthetic reinforcing fibers
Epoxy coatings
Non-shrink grout
Sealer-hardener
Preformed joint filler
Reinforcement supports
[
SD-04 Samples
**************************************************************************
NOTE: Where flat surface finishing is important,
provide a sample installation to train the crew.
**************************************************************************
Slab finish sample]
SD-05 Design Data
Mixture design; G, [_____]
SD-06 Test Reports
Fly ash
Natural pozzolan
SECTION 03311
Page 12