COE CRD-C 94
(1966) Specification for Surface Retarders
1.2
UNIT PRICE CONTRACT
**************************************************************************
NOTE: Remove these paragraphs when lump sum
contract is required.
**************************************************************************
1.2.1
Measurement
Measurement of concrete for payment will be made on the basis of the actual
volume within the pay lines of the structure as indicated on the contract
drawings. Measurement for payment of concrete placed against the sides of
any excavation without intervening forms will be made only within the pay
lines of the structure as shown on the contract drawings. No deductions
will be made for rounded or beveled edges, for space occupied by metal
work, for conduits, for voids, or for embedded items which are less than
0.15 cubic meters 5 cubic feet in volume or 0.09 square meters 1 square foot
in cross section.
1.2.2
Payment
Unless otherwise specified, payment for concrete will be made at the
respective unit prices per cubic meter yard for the various items of the
schedule, measured as specified above, which price shall include the cost
of all labor, materials, and the use of equipment and tools required to
complete the concrete work, except for any reinforcement and embedded parts
specified to be paid separately. Unit price payment will not be made for
concrete placed in structures for which payment is made as a lump sum.
1.3
LUMP SUM CONTRACT
**************************************************************************
NOTE: Remove this paragraph when unit price
contract is required.
**************************************************************************
Under this type of contract concrete items will be paid for by lump sum and
will not be measured. The work covered by these items consists of
furnishing all concrete materials, reinforcement, miscellaneous embedded
materials, and equipment, and performing all labor for the forming,
manufacture, transporting, placing, finishing, curing, and protection of
concrete in these structures.
1.4
SUBMITTALS
**************************************************************************
NOTE: Submittals must be limited to those necessary
for adequate quality control. The importance of an
item in the project should be one of the primary
factors in determining if a submittal for the item
should be required.
A "G" following a submittal item indicates that the
submittal requires Government approval. Some
submittals are already marked with a "G". Only
delete an existing "G" if the submittal item is not
SECTION 03300A