projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for
the Government.] The following shall be submitted in accordance with
Section 01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Installation[; G][; G, [_____]]
Equipment[; G][; G, [_____]]
Electrical Work[; G][; G, [_____]]
Detail drawings containing complete wiring and schematic
diagrams, and any other details required to demonstrate that the
system has been coordinated and will properly function as a unit.
Drawings shall show proposed layout and anchorage of equipment and
appurtenances, and equipment relationship to other parts of the
work including foundation and clearances for maintenance and
of State certificate of barrier performance.
SD-03 Product Data
Vehicle Barriers
A complete list of equipment, materials, including industrial
standards used and how they apply to the applicable component and
manufacturer's descriptive data and technical literature, catalog
document a minimum 1-year successful field operation performance
history for each type of vehicle barrier installed.
Spare Parts
Spare parts data for each different item of material and
shall include a complete list of parts and supplies, with current
unit prices and source of supply.
SD-06 Test Reports
SECTION 02840
Page 5