installed.
1.3
BASIS OF PAYMENT
**************************************************************************
NOTE: Where the basis for bidding is based entirely
on unit price, paragraph BASIS OF BID AND UNIT
PRICES should be deleted and the following paragraph
substituted.
**************************************************************************
1.3.1
Unit Price
The Contracting Officer shall have the right to increase or decrease the
total length linear footage of drilled foundation caissons to be furnished
and installed by changing the foundation caisson elevations, by requiring
the installation of additional caissons, or omission of caissons from the
requirements shown and specified. Whether or not such changes are made,
the Contractor shall be paid at the contract unit price per linear meter
foot (including test caissons) multiplied by the total linear meters feet
of acceptable caissons actually installed provided, however, that in the
event the Contracting Officer requires an increase or decrease in the total
length linear footage of caissons furnished and installed, the contract
unit price will be adjusted in accordance with the CONTRACT CLAUSES.
1.3.2
Full Compensation
Payment in accordance with the above paragraph Unit Price shall constitute
full compensation for furnishing, delivering, handling, and/or installing
(as applicable) all material, labor and equipment necessary to meet
contract requirements applicable to the foundation caissons. The
Contractor will not be allowed payment for rejected caissons.
1.3.3
Load Tests
The contract includes [_____] [_____] -ton caisson load tests. The
Contracting Officer reserves the right to increase or decrease the number
of load tests. Adjustments in the contract price will be made for such
increases or decreases by the amounts bid for "Additional Caisson Load
Test" or "Omitted Caisson Load Test."
1.3.4
Penetration Tests
Contract shall include [_____] penetration tests. The Contracting Officer
reserves the right to increase or decrease the number of penetration tests.
Adjustments in the contract price will be made for such increases or
decreases by the amounts bid for "Additional Penetration Test" or "Omitted
Penetration Test."
1.3.5
Proof Test Holes
Contract shall include [_____] proof test holes. The Contracting Officer
reserves the right to increase or decrease the number of proof test holes.
Adjustments in the contract price will be made for such increases or
decreases by the amounts bid for "Additional Proof Test Hole" or "Omitted
Proof Test Hole."
SECTION 02466A
Page 6