Penetration Test".
1.2.2.3
Proof Test Hole
Contract shall include [_____] proof test holes. The Contracting Officer
reserves the right to increase or decrease the number of proof test holes.
Adjustments in the contract price will be made for each such increase or
decrease by the amount bid for "Additional Proof Test Hole" or "Omitted
Proof Test Hole".
1.2.3
Unit Prices
1.2.3.1
Additional Caisson Lengths
Additional caisson lengths will be paid for at the contract unit price for
"Additional Caisson Length" for each diameter of caisson installed as
approved.
1.2.3.2
Omitted Caisson Lengths
The contract price will be reduced by the amount bid for "Omitted Caisson
Length" for each diameter of caisson omitted as directed.
1.2.3.3
Casings Permanently Left in Place
Steel casings permanently left in place due to contract conditions:
a.
Total pounds of steel beyond casings indicated will be paid for at
the contract unit price per pound for "Additional Steel Casing."
b.
Omitted Casing Steel: The contract price will be reduced by the
amount bid for "Omitted Casing Steel" omitted as directed.
1.2.3.4
Reinforcing Steel for Additional Caisson
Reinforcing steel for additional caisson lengths will be paid for at the
contract unit price for "Additional Caisson Reinforcing Steel" installed as
approved.
1.2.3.5
Reinforcing Steel for Caissons Omitted
The contract price will be reduced by the amount bid for "Omitted Caisson
Reinforcing Steel" omitted as directed.
1.2.3.6
Removal of Rock
Removal of rock within the limit of caissons will be paid for at the
contract unit price for "Removal of Rock" per linear meter foot, for each
diameter of caisson installed. Rock excavation is defined as any hard
dense material that cannot be removed with caisson drilling equipment
having the specified capacity and could only be removed by hand, air tools,
blasting, or other specialized methods.
1.2.3.7
Removal of Obstructions Other Than Rock
Removal of obstructions
other than rock within the limits of the caissons
which cannot be removed
using standard caisson drilling equipment with the
specified capacity will
be paid for at the contract unit price per linear
meter foot for "Removal
of Obstructions" for each diameter of caisson
SECTION 02466A