piles. This list shall be used as the basis for ordering piles. Payment
will be on the basis of length of piling from cutoff elevation to final tip
elevation, established by the requirements specified elsewhere in this
section. Should the total number of piles or number of each length vary
from that specified, an adjustment in the contract price and the time for
completion will be made. If excavation is made adjacent to piling and
below the grade indicated and if piling is driven before backfilling of
over-excavation, no payment will be made for the length of piling equal to
the depth of the over-excavation. No additional payment will be made for
cutting off piles, for any portion of a pile remaining above the cutoff
elevation, or for broken, damaged, or rejected piles. The contract price
shall include [_____] pile load tests.
1.4
EXPERIENCE
The work shall be performed by a firm specializing in the specified
foundation system and having experience installing the specified foundation
system under similar subsurface conditions.
1.5
SUBSURFACE DATA
Subsurface soil data logs are shown [on the drawings] [in the
specifications]. The subsurface [investigation reports] [and] [samples of
materials as taken from subsurface investigations] are available for
examination at [_____].
PART 2
PRODUCTS
2.1
MATERIALS
**************************************************************************
NOTE: Requirements for materials should be edited
or expanded as necessary to include only those
materials to be used for the project.
**************************************************************************
2.1.1
Pressure Treated Piles
**************************************************************************
NOTE: This paragraph covers pressure-treated piles
for marine use or for land or fresh water. Insert
class of piles required: friction or end bearing.
Give elevation below which splices are to be
located. Delete portions not applicable to the
project.
**************************************************************************
Pressure treated piles shall be Douglas fir or Southern pine, clean-peeled,
conforming to ASTM D 25. [Piles shall be in one piece] [Splices will be
permitted] [Splices will not be permitted] [Splices shall be below
elevation [_____]].
2.1.1.1
Marine Piling
**************************************************************************
conditions of high limnoria and pholad hazard exist,
or where oil slicks in harbors may contribute to