Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for [Contractor Quality Control
approval.] [information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] The following shall be submitted in accordance with Section
01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Installation[; G][; G, [_____]]
Drawings, including shop and erection details, collars, shoes,
and splices as required, prior to commencing the work or ordering
materials.
Pile Driving
A complete and accurate record of each driven pile within 3 days
of completion of driving. The record shall indicate the pile
location (as driven), diameter, driven length, embedded length,
final elevations of tip and top, collars, shoes, number of splices
and locations, blows required for each foot of penetration
throughout the entire length of the pile and for the final 150 mm
6 inches of penetration, and the total driving time. The record
shall also include the type and size of the hammer used, the rate
of operation, and the type and dimensions of driving helmet and
pile cushion used. Any unusual conditions encountered during pile
installation shall be recorded and immediately reported to the
Contracting Officer.
SD-03 Product Data
Pile Driving Equipment
Descriptions of all pile driving equipment to be employed in the
work, prior to commencement of pile installations. This shall
include details of the pile hammer, power plant, leads, cushion
material, and helmet.
SD-06 Test Reports
Field Tests and Inspections
A complete report of the load test within [7] [_____] days of
completion of load test, including but not limited to, a
description of the pile driving equipment, driving records for
both test piles and reaction piles, complete test data, analysis
of test data, and recommended allowable design loads based on the
load test results. The report shall be prepared by or under the
direct supervision of a registered professional engineer
experienced in pile load testing and load test analysis, provided
and paid for by the Contractor. A minimum of [14] [_____] days
from submission of the report shall be allowed.
1.3
BASIS OF PAYMENT
**************************************************************************
NOTE: Where the basis for bidding is based on unit