[Blasting[; G][; G, [_____]]]
Submit 15 days prior to starting work.
SD-03 Product Data
Utilization of Excavated Materials[; G][; G, [_____]]
Rock Excavation
Opening of any Excavation or Borrow Pit
Shoulder Construction
Procedure and location for disposal of unused satisfactory
material. Proposed source of borrow material. Notification of
encountering rock in the project. Advance notice on the opening
of excavation or borrow areas. Advance notice on shoulder
construction for rigid pavements.
SD-06 Test Reports
Testing
Borrow Site Testing
of test results, including calibration curves and results of
calibration tests. Results of testing at the borrow site.
SD-07 Certificates
Testing
Qualifications of the commercial testing laboratory or
Contractor's testing facilities.
1.6
SUBSURFACE DATA
Subsurface soil boring logs are [shown on the drawings] [appended to the
SPECIAL CONTRACT REQUIREMENTS]. The subsoil investigation report and
samples of materials taken from subsurface investigations may be examined
at [_____]. These data represent the best subsurface information
available; however, variations may exist in the subsurface between boring
locations.
1.7
CLASSIFICATION OF EXCAVATION
**************************************************************************
NOTE: Inapplicable portions will be deleted. Other
classifications of excavation may be utilized as
required.
**************************************************************************
[No consideration will be given to the nature of the materials, and all
excavation will be designated as unclassified excavation.] [Excavation
specified shall be done on a classified basis, in accordance with the
following designations and classifications.]
1.7.1
Common Excavation
Common excavation shall include the satisfactory removal and disposal of
all materials not classified as rock excavation.
SECTION 02300
Page 17