SECTION 02300
EARTHWORK
10/04
**************************************************************************
NOTE: This guide specification covers the
requirements for earthwork activities for buildings,
utilities, roadways, railroads, and airfields.
Comments and suggestions on this guide specification
are welcome and should be directed to the technical
proponent of the specification. A listing of
technical proponents, including their organization
designation and telephone number, is on the Internet.
Recommended changes to a UFGS should be submitted as
a Criteria Change Request (CCR).
Use of electronic communication is encouraged.
Brackets are used in the text to indicate designer
choices or locations where text must be supplied by
the designer.
This guide specification includes tailoring options
for topsoil and borrow. Selection or deselection of
a tailoring option will include or exclude that
option in the section, but editing the resulting
section to fit the project is still required.
**************************************************************************
PART 1
GENERAL
**************************************************************************
NOTE: Consult with a soils engineer while editing
this section to determine specific requirements for
each job.
The following information will be indicated on the
1.
Surface elevations, existing and new;