Prior to final inspection and transfer of the completed facility; all
reports, statements, certificates, and completed checklists for testing,
submitted to and approved by the Contracting Officer as specified in
applicable technical specification sections.
1.5
OPERATION AND MAINTENANCE MANUALS
be clearly differentiated and shall be separately indexed.
1.6
FINAL CLEANING
The premises shall be left broom clean. Stains, foreign substances, and
temporary labels shall be removed from surfaces. Carpet and soft surfaces
shall be vacuumed. Equipment and fixtures shall be cleaned to a sanitary
condition. Filters of operating equipment shall be [cleaned] [replaced].
downspouts. Paved areas shall be swept and landscaped areas shall be raked
clean. The site shall have waste, surplus materials, and rubbish removed.
The project area shall have temporary structures, barricades, project
signs, [____] and construction facilities removed. A list of completed
clean-up items shall be submitted on the day of [final inspection] [_____].
PART 2
PRODUCTS (NOT USED)
PART 3
EXECUTION (NOT USED)
-- End of Section --
SECTION 01780A
Page 15