[_____]
[_____]
[_____]
]
][1.5.8
QC Administrative Assistant
**************************************************************************
NOTE: Use this paragraph for a project requiring a
large volume of submittals.
**************************************************************************
Provide an Administrative Assistant at the work site until the work has
been accepted. The primary duty shall be to assist the QC Manager in
reports and meeting minutes. After primary duties are accomplished, other
duties may be assigned provided the duties do not interfere with primary
duties.
][1.5.9
Underwater QC Team
**************************************************************************
NOTE: This paragraph to be used only when the
inspection of underwater work is required.
**************************************************************************
Provide Underwater QC (UWQC) Team at the work site to perform underwater
surveillance and inspection for the Contractor. The UWQC Team divers shall
have current commercial diver's license, with a minimum of five (5) years
experience with underwater inspection. The personnel make up of the UWQC
team shall comply with EM 385-1-1, OSHA and local requirements for Contract
diving operations. The UWQC team shall comply with all the applicable
safety requirements of EM 385-1-1, OSHA and local requirements for Contract
diving operations. The UWQC lead diver shall be thoroughly familiar with
the design plans and specifications to sufficiently understand the
engineering aspects of the underwater construction and to be able to
recognize and document potential problem areas such as improperly
constructed or defective areas. The UWQC Team shall provide all necessary
equipment to conduct surveillance and inspection services, including
diver's equipment, dive boat, communication equipment, and
photographic/video equipment. Diver(s) shall be equipped to maintain
two-way communication with QC personnel during diving operations. A report
including photographs and/or videos shall be prepared and submitted with
the QC report after each dive. Frequency of underwater surveillance and
inspection shall be [_____] during installation and including final
inspection. The UWQC Team shall be an independent third party hired
directly by the Prime Contractor, and shall have no involvement with the
design, preparation of Contract, or installation of work.
]1.6
QUALITY CONTROL (QC) PLAN
1.6.1
Construction Quality Control (QC) Plan
1.6.1.1
Requirements
Provide, for acceptance by the Contracting Officer, a Construction QC Plan
submitted in a three-ring binder that includes a table of contents, major
sections identified with tabs, with pages numbered sequentially, and that
documents the proposed methods and responsibilities for accomplishing
SECTION 01450N