NOTE: Designer must coordinate with facility
personnel for ground clearance and establish
clearances to be shown on drawings.
**************************************************************************
e.
Loops shall be formed in the aerial cable at all points of
connection and at all poles to prevent damage from thermal stress
and wind loading. The communication cable shall be protected from
chafing and physical damage with the use of spiral cut tubing and
PVC tape, or plastic sleeves. The ground clearance of installed
cabling shall be as shown.
3.1.4
Enclosure Penetrations
All enclosure penetrations shall be from the bottom and shall be sealed
with rubber silicone sealant to preclude the entry of water.
3.2
TESTING
3.2.1
General
The Contractor shall provide all personnel, equipment, instrumentation, and
supplies necessary to perform all testing.
3.2.2
Government Furnished RFCE Test
The Contractor shall test the Government furnished RFCE and certify that
the equipment is in calibration and functioning correctly.
3.2.3
Contractor's Field Test
The Contractor shall verify the complete operation of the stand-alone
one-way radio control system. The Contractor's Field Test shall include an
error rate test. The Contractor shall perform the test by sending 100,000
commands and measuring the error rate. The error rate shall be not greater
than 5 out of 100,000. The Contractor shall prepare a report containing
results of the field test.
-- End of Section --