SECTION 16526A
AIRFIELD AND HELIPORT LIGHTING AND VISUAL NAVIGATION AIDS
12/04
**************************************************************************
NOTE: This guide specification covers the
requirements for lighting and visual navigation aids
for airfields and heliports.
Comments and suggestions on this guide specification
are welcome and should be directed to the technical
proponent of the specification. A listing of
technical proponents, including their organization
designation and telephone number, is on the Internet.
Recommended changes to a UFGS should be submitted as
a Criteria Change Request (CCR).
Use of electronic communication is encouraged.
Brackets are used in the text to indicate designer
choices or locations where text must be supplied by
the designer.
**************************************************************************
PART 1
GENERAL
**************************************************************************
NOTE: If the existing facility is to be operational
during construction, a scheduling plan properly
coordinated with the airfield or heliport users
should be developed and included as part of the bid
package. Maximum outage time allowed should be
specified for critical lighting, visual navigational
aids and utility systems. Minimum advance notice
(48 hrs, 72 hrs, etc.) for proposed outages should
be specified. Consider transfer of control from the
Control Tower to the alternate control point (vault)
to maintain the mission for limited times during
construction and to minimize mission disruption and
potential cost growth during construction. If this
is not possible, the scheduling can be delegated to
the construction phase of the project by inserting