1.3
SYSTEM DESCRIPTION
**************************************************************************
electrical power system project.
Coordinate with Section 16311A MAIN ELECTRIC SUPPLY
STATION AND SUBSTATION; Section 16370A ELECTRICAL
DISTRIBUTION SYSTEM, AERIAL; Section 16375A
ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND; Section
16415A ELECTRICAL WORK, INTERIOR.
**************************************************************************
The power system covered by this specification consists of:
[_____].
1.4
QUALIFICATIONS
1.4.1
System Coordinator
System coordination, recommended ratings and settings of protective
professional electrical power engineer with a minimum of [3] [_____] years
of current experience in the coordination of electrical power systems.
1.4.2
System Installer
Calibration, testing, adjustment, and placing into service of the
service engineer or independent testing company with a minimum of two years
1.5
DELIVERY, STORAGE, AND HANDLING
Devices and equipment shall be visually inspected when received and prior
to acceptance from conveyance. Stored items shall be protected from the
environment in accordance with the manufacturer's published instructions.
Damaged items shall be replaced.
1.6
PROJECT/SITE CONDITIONS
**************************************************************************
NOTE: Unusual service conditions for altitude start
above 1005 m (3300 feet) for most apparatus.
Unusual ambient temperature ranges are minus 30 to
40 degrees C, but other ambients may apply.
Frequency is generally 60 Hz, although 50 Hz may
also be standard. Fungus control for electrical
devices is required only in tropical areas.
Provide seismic requirements, if a Government
designer is the Engineer of Record, and show on the
drawings. Delete the inappropriate bracketed
phrase. Sections 13080, 15070A and 16070A, properly
edited, must be included in the contract documents.
**************************************************************************
Devices and equipment furnished under this section shall be suitable for
the following site conditions. Seismic details shall [conform to Sections
13080 SEISMIC PROTECTION FOR MISCELLANEOUS EQUIPMENT, 15070A SEISMIC
SECTION 16475A