instruments calibrated or tested. For instruments calibrated by
the manufacturer on a routine basis, in lieu of third party
(a) Maintain up-to-date instrument calibration instructions and
procedures for each test instrument.
(b) Identify the third party/laboratory calibrated instrument to
verify that calibrating standard is met.
[2.3.2
Integral Assembly Test
**************************************************************************
NOTE: Coordinate with paragraph "Factory Test
Reports" prior to use of option requiring testing of
integral assemblies.
**************************************************************************
Switchgear and substation transformer shall be tested as an integral
assembly at the transformer manufacturer's test facility. Once acceptance
of test results is received, ship switchgear and substation.
]2.3.3
Switchgear Design Tests
IEEE C37.20.2 or IEEE C37.20.3 as applicable. Furnish documentation
showing the results of design tests on a product of the same series and
rating as that provided by this specification. Required tests shall be as
follows:
a.
Design Test
[1.
Dielectric test]
[2.
Rated continuous current test]
[3.
Short-time current withstand tests]
[4.
Short-circuit current withstand tests]
5.
Mechanical endurance tests
6.
7.
Rod entry tests
[8.
Rain test for outdoor MV switchgear]
2.3.4
Switchgear Production Tests
IEEE C37.20.2 or IEEE C37.20.3 as applicable. Furnish reports which
include results of production tests performed on the actual equipment for
this project. Required tests shall be as follows:
a.
Production Test
1.
Dielectric test
2.
Mechanical operation tests
SECTION 16361N
Page 36