Switches, air-break.
Switchgear, metal-clad.
Switchgear, metal-enclosed interrupter.
3.5.10
Operating Tests
After the installation is completed, and at such time as the Contracting
Officer may direct, the Contractor shall conduct operating tests for
approval. The equipment shall be demonstrated to operate in accordance
with the requirements herein. An operating test report shall be submitted
in accordance with paragraph TEST REPORTS.
3.6
MANUFACTURER'S FIELD SERVICE
3.6.1
Onsite Training
The Contractor shall conduct a training course for the operating staff as
designated by the Contracting Officer. The training period shall consist
of a total of [_____] hours of normal working time and shall start after
the system is functionally completed but prior to final acceptance tests.
The course instruction shall cover pertinent points involved in operating,
starting, stopping, servicing the equipment, as well as all major elements
instructions shall demonstrate all routine maintenance operations. A
[_____] [BETA] [VHS] format video tape of the entire training session shall
be submitted.
3.6.2
Installation Engineer
After delivery of the equipment, the Contractor shall furnish one or more
field engineers, regularly employed by the equipment manufacturer to
supervise the installation of the equipment, assist in the performance of
the onsite tests, initial operation, and instruct personnel as to the
operational and maintenance features of the equipment.
3.7
ACCEPTANCE
Final acceptance of the facility will not be given until the Contractor has
successfully completed all tests and after all defects in installation
material or operation have been corrected.
-- End of Section --
SECTION 16311A
Page 76